IMG_20160818_112649-1280x720.jpg

  • ​Project location: Freiburg, Germany​
  • Client: Freiburg Regional Council​
  • Processing time: 2016 - dato​

​

  • Type: single-tube Road tunnel in the Two-way traffic (RQ 11t)​
  • Length: 844 m​
  • Overlap: max. approx. 40 m ​
  • Breakdown bays: 2​

​Areas of responsibility​

  • § 43 HOAI OP Lph. 1-3​
  • § 51 HOAI TP Lph. 2-3​
  • Preparation of geotechnical / tunnel construction​ Report​

​


Rüßdorf1
Rüßdorf2
Rüßdorf3
Rüßdorf4

  • ​Project location: Leipzig, Lehna mill ​
  • Client: DB InfraGO AG Erfurt, EBA Hall
  • Processing time: 2024 ​
  • Utilization: Partial renewal of tunnel Rüßdorf​
  • Length: 264 m ​
  • Diameter: single-track existing tunnel to EBO ​

Areas of responsibility​

  • Static-constructive testing ​
  • Checking the implementation planning​
  • Project duration: planned until 2025​


Kein-Titel-1920-x-1440-px-4-1280x960.jpg

  • ​Project location: Dresden, Germany​
  • Client: Landesbetrieb für Straßenbau und Traffic Dresden​
  • Processing time: 2016 - dato​
  • Type: twin-tube road tunnel​
  • Length: approx. 3.3 km​

​

Areas of responsibility​

  • § 43 HOAI OP Lph. 1-3, 5, 6 (structural retrofitting)​
  • § 51 HOAI TP Lph. 2-6 (structural retrofitting)​

​


Bürgerwald1
Bürgerwald2
Bürgerwald3
Kein Titel (1920 x 1440 px)

  • ​Project location: Waldshut - Tiengen and Lauchringen​
  • Client: The Autobahn GmbH of the Federal Government,
    Southwest branch Stuttgart​
  • Processing time: 2024 - dato​
  • Type:
    • BWT - 2-strip vault cross-section,including two rescue tunnels
    • HÄT- 3-lane frame structure​
  • Length:
    • BWT - 1,462 m​
    • HÄT - 150 m ​

​

​

Areas of responsibility​

  • Planning services for the concrete and Joint renovation of tunnel structures ​
    according to ZTV-ING​
  • Project planning HOAI, phases 1-3, 5 and 6​
  • Structural design HOAI, 2-3 and 6 ​

​


IMG_2916
OKL_20240702-DB-_MG_0372-1
20240702-DB-_MG_0018-1-min
IMG_2915

  • ​Project location: Henstedt-Ulzburg, Germany ​
  • Client: TenneT TSO GmbH, Bayreuth
  • Processing time: 2019 - dato
  • Utilization: 380 kV underground cable routeEast Coast pipeline to connect Offshore wind turbines
  • Length: 2 x 965 m​
  • Diameter: Diameter 2.6 m ​
  • Overlap: up to approx. 10 m ​
  • Machine type: Hydroshield / Slurry shield​

Areas of responsibility​

  • Tender planning​
  • Invitation to tender​
  • Participation in the awarding of contracts​
  • Construction supervision and tunnel construction Advice for the construction phase of the continuous Drives​
  • Project duration pipe jacking: July to October 2024​


Kein Titel (1920 x 1440 px)
50hz Startschacht_112022

  • Project location: Berlin, Germany​
  • Client: 50Hertz Transmission GmbH Berlin​
  • Processing time: 2015 - dato​
  • Utilization: Cable tunnel​
  • Length: 6,700 m, 1 tube​
  • Diameter: 3.0 m / 3.6 m (inside/outside)​
  • Overlapapprox. 25 m to 30 m​
  • Machine type: TVM - Hydro shield​
  • Building volume: 53 million​

​

Areas of responsibility ​

  • HOAI object planning of engineering structures: Lph. 1 - 7​
  • HOAI structural design of civil engineering structures: Lph. 3​
  • Technical equipment of the shaft structures​
  • Safety and health protection​
  • Preparation of the tender documents​
  • Participation in awarding​
  • TBM consultant​
  • Process controlling​


Bild-Innovation-1280x960.jpg

  • Project location: Ibbenbüren, Germany​
  • Client: RAG Anthrazit Ibbenbüren GmbH​
  • Processing time: 2018 - dato​
  • Type: Mine water channel​
  • Utilization: Tunnel for mine water​
  • Length: approx. 7.2 km​
  • Diameter: 3,60 m inside​
  • Overlap: approx. 7 m to max. 95 m​
  • Machine type: EPB / Hydro​

Areas of responsibility​

  • Planning, site management and local construction supervision Rescue concept​
  • Project planning shield tunnel, Lph. 3 - 4, 5 - 8​
  • Structural design of the shield tunnel, Lph. 1 - 3, 4 - 6 ​
  • TBM consultant​
  • Process controlling​


Hanau Maschine mit Logo_012024
Hanau Rohrstrang fertig_022024
Hanau Rohrvortrieb_Einhebung Maschine_012024
Hanau Startschacht_022024
IMG-20240123-WA0015
IMG-20240123-WA0016

  • Project location: Hanau, Germany​
  • Client: Hanau Netz GmbH, Hanau /Engineering office Becker & Partner GmbH, Bad Soden-Salmünster​
  • Processing time: 2021 - 2024​
  • Utilization: 20 kV power line, Establishment of a data center
  • Length: approx. 240 m​
  • Diameter: Diameter 1.96 m​
  • Overlap: up to approx. 6.0 m ​
  • Machine type: Hydro shield​

Areas of responsibility​

  • Engineering support​
  • Support pressure calculations​
  • Creation UiG​
  • Process controlling during the tunnelling work​
  • BVB services according to VV-Bau​


Rothenstein_Zuschnitt1
Rothenstein1

  • ​Project location: Rothenstein
  • Client: Thuringian State Office for Construction and Traffic, Road Construction
  • Processing time: 2018 - 2021
  • Type: Road tunnel two tubes with 2 lanes
  • Length: 346 m mined construction method
    16 m in open construction
    34 m in semi-open construction
  • Diameter: 9,5 m
  • Overlap: 30 m

​Areas of responsibility​

  • Structural inspection of the tunnel structure, precuts, retaining walls north portal, operations building, pollutant basin, permanent anchors and reinforced concrete re-storage south portal

​


Kohlbergtunnel-e1739813742736.jpg

  • ​Project location: Pirna, Germany​
  • Client: DEGES​
  • Processing time: 2018 - dato​
  • Type: single-tube road tunnel
  • Utilization: Oncoming traffic
  • Diameter: Jaw profile largest clear width 14.70 m​
  • Length: 340 m, of which 300 m are mined​
  • Overlap: approx. 30 m
  • Machine type: Excavator drive double-headed elm tunnel drive

​

Areas of responsibility​

  • Review of the design documents​

  • ​Review of the tender planning ​

  • Tunnel construction consulting and control for Tunneling and concreting work during and in the Follow-up to the drive​

  • Participation in the determination of Tunneling classes, excavation and Safety measures​

  • Assessment of the rock mass, evaluation of the Deformation measurements and checking the found rock properties with regard to the effects on the propulsion and the Inner shell​

  • EPLASS plan management system, checking the Implementation planning and concepts from from a tunnel construction point of view.​

​


Business hours

Contact us

You can contact us here.

+49 (0)234 / 9 70 77-0Business hours: Monday to Friday, 08:00 - 17:00

Locations

Bochum & Munich



Head office Bochum
Konrad-Zuse-Strasse 18
44801 Bochum

+49 (0)234 / 9 70 77-0info@imm-bochum.de

Munich branch
Nymphenburger Str. 20a
80335 Munich

+49 (0)89 / 890 65 98-20info@imm-muenchen.de

Social Media

IMM also on LinkedIn

Take a look at LinkedIn to make sure you don't miss anything.


en_USEN